Electrical Installation

Common Mistakes During Electrical Installation

Many electrical installation mistakes in Dubai are small: a cable too light for an AC circuit, an indoor socket fitted on the roof, a distribution board with no labels, or a handover with no test results. Each is far easier to put right while the walls are still open than after the paint is dry.

This guide is for villa and apartment owners, landlords and small-business owners commissioning or finishing new wiring, a renovation, an extension or a fit-out. Each mistake comes with what goes wrong, why it matters in Dubai and what to ask, followed by a handover checklist and advice on inspections.

The rulebook your contractor should be working from

In Dubai, the reference document is DEWA’s Regulations for Electrical Installations. This guide refers to the 2017 edition, which replaced the 1997 edition. The regulations refer generally to IET wiring regulations and IEC documents, with DEWA’s own requirements prevailing on any conflict.

A DEWA circular dated January 2022 explains that the electrical design clauses from these regulations are included in the Dubai Building Code, mainly in Parts G and K, and that compliance is checked when drawings are submitted for DEWA design approval. DEWA revises its documents from time to time, so ask your contractor which edition and code they are designing to.

The electrical installation mistakes in Dubai worth checking for

1. Hiring someone DEWA does not know, and skipping the paperwork

What goes wrong. The job goes to the lowest quote without checking whether the firm can submit work to DEWA. No load schedule is prepared, and nothing is tested before the walls are closed.

Why it matters here. DEWA’s 2017 regulations require consultants and electrical contractors to enrol with DEWA before carrying out design or installation work in Dubai, and to have enough qualified engineers and technicians to supervise and test the work before power is connected. The contractor must test the whole installation before DEWA inspects, tests and approves it for supply, and load distribution schedules go to DEWA for approval in a set format. Whether an alteration needs a fresh DEWA submission depends on the job.

What to ask or check.

  • Is your firm enrolled with DEWA, and under what name?
  • Does this job need a DEWA submission? If not, why not? Ask for the answer in writing.
  • Who will test the installation, and will I get the test certificate?

2. Sizing circuits for an average day instead of a Dubai summer

What goes wrong. AC units share circuits, kitchen appliances sit on one overloaded run, and cables are chosen for today’s load. The result is warm cables, nuisance tripping and a board with no room to grow. If you already live with the symptoms, read why breakers keep tripping.

Why it matters here. DEWA’s 2017 regulations assume a maximum outdoor shade temperature of 48 °C and correct cable ratings for how and where cables are installed. They also set these rules:

  • Each room air-conditioning unit has its own final sub-circuit from the distribution board, sized to the connected load, with at least a 20 A breaker and 4 mm² wiring.
  • Voltage drop from the point of supply to any equipment must not exceed 4% of nominal voltage unless otherwise specified.
  • Outside kitchens, a radial circuit may serve at most five 13 A switched socket-outlets on a 20 A breaker; a ring circuit may serve up to ten on a 30 A breaker.

The cable-sizing tables also carry a note to assess both initial and anticipated future demand when choosing cable sizes and breaker ratings.

What to ask or check.

  • Ask for the load schedule. Each AC unit should appear as its own circuit.
  • Ask how many sockets are on each kitchen circuit.
  • Ask whether the cable sizes allow for heat in ceiling voids and on the roof.

3. Treating earthing and RCD protection as optional extras

What goes wrong. The earth connection is improvised, neutral and earth are joined where they should not be, or socket circuits go in without residual-current protection because “the old board didn’t have it.”

Why it matters here. Earthing and RCD protection are mainly about protecting people. DEWA’s 2017 regulations set out the following:

  • Every consumer installation must have its own earthing system within the plot limits. The main earthing arrangement is TN-S, and neutral and earth conductors must be kept separate throughout.
  • Water mains must not be used for earthing.
  • Main earth electrode resistance must not exceed 1 ohm, and resistance from any point of the earth continuity conductor back to the main electrode must not exceed 0.5 ohm.
  • Additional protection by an RCD (also called an ELCB, or an RCBO when combined with a breaker) with a rated residual current of no more than 30 mA is required for socket-outlets rated 20 A or less (unless exempt), for mobile equipment up to 32 A used outdoors, and for cables concealed in walls at a depth of less than 50 mm.
  • Water heater circuits must be protected by a 30 mA device, and cooker control circuits are fed through a 100 mA device on a separate sub-circuit.

What to ask or check.

  • Where is the earth electrode, and what resistance did it measure?
  • Which circuits are protected by 30 mA devices? You should be able to point to them on the board.
  • Is there an “RCD quarterly test notice” at or near the main board? The 2017 regulations require one at the origin of the installation. Ask the contractor to show you each RCD’s test button so you can follow the notice.

4. Using indoor fittings outdoors and guessing in wet areas

What goes wrong. Standard switches and sockets end up on terraces, roofs and garden walls, plastic conduit is chosen without asking how it handles heat, and bathroom switches go wherever is convenient.

Why it matters here. Sun, dust and heat are hard on outdoor electrics. DEWA’s 2017 regulations require weather-protected IP55 switches and socket-outlets outdoors. For conduit, they require PVC conduit to be high-impact rigid and suitable for ambient temperatures up to 48 °C, and steel conduit, where used, to be hot-dip galvanised.

In bathrooms, the water heater control switch must sit immediately outside the bathroom or toilet, and extra-low-voltage items such as shaver sockets and mirror lights need a safety isolating transformer.

What to ask or check.

  • What IP rating do the outdoor sockets, switches and lights have? Check the marking on the product or box.
  • What conduit is going on the roof, and what is it rated for?
  • Where will the water heater switch go?

5. A distribution board nobody can read

What goes wrong. Breakers are unlabelled or marked “spare,” so nobody can find the right circuit during a fault.

Why it matters here. DEWA’s 2017 regulations require each breaker or fuse in a distribution board to be labelled to show what it controls; labels may be in English and Arabic. Diagrams, charts or schedules should be kept at or near each board where required, together with warning and next-inspection labels, and the top of the board should be no higher than 2 m. DEWA’s final checks include confirming that equipment and conductors match the approved drawings.

What to ask or check.

  • Is every breaker labelled with the room or appliance it serves?
  • Is there a circuit chart inside or beside the board?
  • Ask for drawings updated to match what was actually installed, and keep them with the property papers.

6. Signing off without test results

What goes wrong. The lights work, the invoice arrives, and nobody has seen a test sheet. Faults inside the walls stay hidden.

Why it matters here. DEWA’s 2017 regulations name insulation resistance, continuity and earth electrode resistance tests, recorded on an Inspection & Testing Certificate (Appendix 3). The certificate’s checklist covers:

  • insulation resistance at 500 V DC between conductors and to earth;
  • continuity of each protective conductor, and of ring circuits;
  • single-pole switches and breakers connected in the phase conductor only;
  • visual checks and tests on every RCD/ELCB;
  • IP ratings of barriers and enclosures;
  • terminations, colour codes, circuit identification and caution labels.

The certificate is submitted through DEWA’s online connection system, and DEWA verifies the results during its inspection.

What to ask or check.

  • Ask for a copy of the completed test certificate before the final payment.
  • Check that it shows measured values, not just ticks, and is signed and dated.

7. Loading one phase and leaving the others light

What goes wrong. In a three-phase villa, most single-phase loads end up on one phase, which runs hot and trips while the others have spare capacity.

Why it matters here. DEWA’s 2017 regulations require lighting, socket-outlets, water heaters and single-phase air conditioners to be spread across the phases as evenly as possible. No more than two window-type AC units may be connected to a single-phase supply; three or more must be balanced across the three phases.

What to ask or check.

  • Ask to see how circuits are split across phases on the load schedule.
  • If one phase keeps tripping after the job, ask the contractor to measure the current on each phase.

8. Leaving no room for an EV charger or the next AC unit

What goes wrong. The board is full and the incoming cable is sized for today, so adding an EV charger, an extra AC unit or smart-home equipment later can mean a board upgrade or a new board.

Why it matters here. As noted under mistake 2, DEWA’s 2017 regulations ask designers to allow for anticipated future demand.

EV charging has its own document: DEWA’s EV Charging Technical Regulations (Version 1.0, May 2025) specify a 30 mA class A RCD for chargers, an IP54 protection rating, a TN earthing system, and installation in line with the IET Code of Practice and BS 7671. For the electrical connection, they direct applicants to DEWA-enrolled consultants or contractors. The document is written mainly around charging stations and sets out no separate process for a private villa charger, so ask your contractor what applies before you buy one.

What to ask or check.

  • How many spare ways will the board have at handover?
  • If an EV charger is likely, can a cable route or supply allowance go in now?
  • Is the incoming supply big enough for the charger plus the existing AC load?

9. Treating AC isolators and outdoor unit connections as an afterthought

What goes wrong. The AC units are wired at the last minute, with no proper local switch or with one placed out of reach.

Why it matters here. DEWA’s 2017 regulations call for room AC units other than window types to be controlled by a double-pole switch with a flex outlet next to the unit, and for double-pole switches for AC units and water heaters to be mounted 125 cm above finished floor level. AC units also need under-voltage protection that cuts out at 75% of nominal voltage and resets automatically after a set delay. For refrigerant lines, drainage and placement, see the separate guide to AC installation mistakes.

What to ask or check.

  • Is there a local double-pole switch beside each AC unit?
  • Does the AC equipment have the required under-voltage protection, and where is it?

Your handover checklist

Use this list before the final payment. If you cannot tick an item, ask the contractor to explain or fix it.

CheckWhat you should see or receive
Contractor statusThe firm’s DEWA enrolment and, where the job needs one, the DEWA submission or approval reference
Test certificateA signed Inspection & Testing Certificate with measured values for insulation resistance, continuity and earth electrode resistance, with earth readings within the limits under mistake 3 (main electrode no more than 1 ohm, earth continuity no more than 0.5 ohm)
RCD protection30 mA devices you can identify on the board for socket circuits and water heaters, plus the quarterly RCD test notice
Board labellingEvery breaker labelled and a circuit chart at or inside the board
AC circuitsOne circuit per AC unit on the schedule and a local switch beside each unit
Phase balance (villas)The load schedule showing circuits split across the three phases
Outdoor fittingsIP55-rated switches and sockets on terraces, roofs and garden walls
BathroomsThe water heater switch outside the bathroom
DrawingsDrawings that match what was actually installed
Spare capacitySpare ways on the board and a note of any EV or extra AC allowance

When to book an inspection

DEWA’s 2017 regulations tie periodic inspection frequency to the installation’s type, use, maintenance and external influences, and require industrial and commercial installations to be inspected at least every two years by an independent consultant or contractor. The same section sets no fixed interval for homes, but the board should carry a next-inspection label.

A check by someone other than the contractor who did the work is sensible when:

  • you have bought or are renting out a property with an unknown electrical history;
  • the handover arrived without a test certificate, or the certificate shows ticks but no readings;
  • breakers trip repeatedly, sockets or switches feel warm, or you notice a burning smell (in that case, switch off and call an electrician first);
  • you are planning a major new load such as an EV charger or extra AC units.

You can book a safety inspection with Al Ghubaiba’s licensed electricians and receive a written report with recommendations. For an office, shop or warehouse, see office and commercial installations.

Frequently asked questions

Do the DEWA regulations only matter for new buildings?

No. They also cover testing and periodic inspection of existing installations. Whether an alteration needs a DEWA submission depends on its scope; get your contractor’s answer in writing.

What paperwork should I keep after the job?

Keep the signed test certificate, the load schedule, the as-installed drawings, any DEWA approval reference and the contractor’s guarantee terms. They let the next electrician understand the installation without opening walls.

Is one RCD at the main board enough?

Not necessarily. DEWA’s 2017 regulations call for 30 mA protection on particular circuits and a 100 mA device on cooker control circuits (see mistake 3). Ask which device protects which circuit.

Can I add an EV charger to my existing villa supply?

Possibly, depending on the spare capacity of your supply and board once the AC load is counted. Get a load assessment from a DEWA-enrolled contractor first.

Planning an installation or renovation?

The easiest time to avoid these mistakes is before the first cable is pulled. Take the questions under each mistake to your contractor before work starts, and run the handover checklist before you make the final payment.

If you would rather have one contractor handle the wiring, the distribution board and the final testing, Al Ghubaiba’s electrical installation service covers villas, apartments and offices, with licensed, insured technicians. You can put the questions in this guide to us, as you would to any contractor.

For smaller jobs, an electrician in Dubai from our team can help. To discuss your project, call +971 55 355 8644 or get a quote. Quotes are free.